Project Period
1996 – 1998
Plant Owner
Parakaya Plywood Sdn Bhd
Plant Details
6.0MW 50 tons/hr boiler for Wood Waste Fired Power Plant at 37 barg, 435°C with travelling grate, fully condensing turbine.
Plant Objective
To generate 6.0MW nett Electricity output using wood waste and simultaneously export power to neighbouring plywood mill.
Plant Location
Keningau, Sabah, East Malaysia
Requirements
Internal Consumption: 700 kW
Power For Production: 5,300 kW
Power Required: 6,000 kW